Project Milestone

Description (Days from Appointed Date)

As per CA

With Grace Period of 90 days as per Clause 12.3.2 of CA

Actual

Remarks

Current Status

Physical Progress (%)

Schedule Date

Physical Progress (%)

Achieved Date

Milestone I

180 Days

20%

28.11.2022

26.02.2023

20.00%

20.12.2022

22

 

Milestone II

365 Days

35%

01.06.2023

30.08.2023

35.00%

13.04.2023

-49

 

Milestone III

550 Days

75%

03.12.2023

02.03.2024

 

 

 

68.00%

Schedule Completion

730 Days

100%

31.05.2024

29.08.2024

 

 

 

Status of Highway work:

Sl. No.

Items

Scope (In Km)

Completed
(in Km)

Balance

1

C&G

43.120

38.000

5.120

2

Embankment Top

43.120

36.880

6.240

3

Subgrade Top

43.120

35.110

8.010

4

GSB

43.120

34.520

8.600

5

CTB

43.120

33.480

9.640

6

AIL

43.120

33.190

9.930

7

DBM

43.120

32.580

10.540

8

BC

45.500

8.250

37.25

Status of Structures:

Sl. No.

Items

Total Number of Structures

Status

Completed

In Progress

Balance

1

Major Bridge

4

-

4

-

2

Minor Bridge

19

16

1

2 nos. (Descope)

3

Culverts

93

91

-

2

4

Viaduct

2

-

2

-

5

VUPs

6

3

3

-

6

VOPs

7

2

3

2 nos. (Descope)

7

LVUPs

15

12

3

-

8

AUPs

1

-

1

-

9

Monkey Canopies

2

-

-

2

10

Interchanges

5

1

4

-

11

Way Side Amenities

-

2 nos. (Descope)

12

ROB

1

-

1

-

SI. No.

Structure Type

Design Chainage

Span Arrangement

Length

Current Status

1.

Viaduct

300+382

LH= 17X35.7+1X37.2
RHS= 1X37.2+15X35.7+1X34.5+1X36.9

644.10

In progress

2.

Viaduct (AUP)

329+900

1x30

30

In progress

3.

Viaduct

336+320

6X35

210

In progress

4.

Major Bridge

307+308

1X35+1X40+1X35

110

In progress

5.

Major Bridge

319+990

11X30

330

In progress

6.

Major Bridge

322+023

4X35

140

In progress

7.

Minor Bridge

330+575

3X40

120

In progress

8.

ROB

299+930

(1X18+3X36+1X18)

144

In progress

9.

VOP

294+577

2x30.25

60.5

In progress

10.

VOP

301+230

2X30.25

60.5

In progress

11.

VOP

305+980

2X30.25

60.5

In progress

12.

VOP

309+473

2X30.25

60.5

Completed

13.

VOP

320+450

2x33x5.5

66

Descope

14.

VOP

320+750

2x33x5.5

66

Descope

15.

VOP

322+750

2X30.25X5.50

60.50

Completed

16.

LVUP

296+200

1x12

12

Completed

17.

LVUP

304+070

1x12

12

Completed

18.

LVUP

312+770

1x12

12

Completed

19.

LVUP

319+367

1x12

12

In progress

20.

LVUP

324+783

1x12

12

Completed

21.

LVUP

325+860

1x12

12

Completed

22.

LVUP

326+025

1x12

12

Shifted to 330+670 (Work in Progress

23.

LVUP

326+300

1x12

12

In progress

24.

LVUP

327+280

1x12

12

Completed

25.

LVUP

329+070

1x12

12

Completed

26.

LVUP

330+258

1x12

12

Completed

27.

LVUP

332+065

1x12

12

Completed

28.

LVUP

332+500

1x12

12

Completed

29.

LVUP

334+700

1x12

12

Completed

30.

LVUP

336+624

1x12

12

Completed

31.

VUP

311+544

2x50.50

101

In progress

32.

VUP

314+961

2x25.50

51

In progress

33.

VUP

316+920

1x34

34

Completed

34.

VUP

317+848

1x34

34

Completed

35.

VUP

318+450

2x25.50

51

In progress

36.

VUP

323+930

1x20

20

Completed

37.

MNB

293+720

1x35

35

Completed

38.

MNB

294+940

1x15

15

Completed

39.

MNB

296+431

1x10

10

Completed

40.

MNB

296+767

1x25

25

DE scope

41.

MNB

296+965

1x25

25

DE scope

42.

MNB

297+996

1x15

15

Completed

43.

MNB

301+762

1x8

8

Completed

44.

MNB

302+150

1x8

8

Completed

45.

MNB

303+655

1x10

10

Completed

46.

MNB

304+412

1x25

25

Completed

47.

MNB

309+915

1x30

30

Completed

48.

MNB

311+400

1x30

30

Completed

49.

MNB

312+100

1x7

7

Completed

50.

MNB

314+620

1x15

15

Completed

51.

MNB

317+677

1x15

15

Completed

52.

MNB

318+810

1x10

10

In progress

53.

MNB

322+930

1x12

12

Completed

54.

MNB

326+672

1x10

10

Completed

55.

MNB

328+500

1x12

12

Completed

56.

Interchange

310+568

2X33

66

Completed

57.

Interchange

319+478

2x20x5.5

40

In progress

58.

Interchange

319+367

1x12x5.5

12

In progress

59.

Interchange

On Merged Section

1x12x5.5

12

In progress

60.

Interchange

337+100

2x20x5.5

40

In progress

FRL Details:

Chainage

Level (in meter)

From

To

Starting Chainage

Ending Chainage

Ch. 293+000

Ch. 338+500

838.580

972.931

Land Acquisition Status:
  • Total No. of villages : 24 Nos.
  • {Dist- Koraput, CALA-Dasamantpur (5 Villages), CALA- Koraput (2 Villages), CALA-Semiliguda (12 Villages) & CALA-Pottangi (5 Villages)}
  • Total Land Required : 378.463 Ha
  • Govt. Land : 76.063 Ha
  • Forest Land : 9.227 Ha
  • Private Land : 293.173 Ha
  • Private land acquisition : 3G completed for 293.173 Ha
  • Compensation approved : Rs.188.44 Cr.
  • Compensation Deposited with CALA : Rs.188.44 Cr.
  • Compensation amount disbursed : Rs.167.11 Cr.
  • Balance Amount to be disbursed : Rs.21.34 Cr.
Forest diversion:
  • Stage-I Clearance for main forest diversion proposal obtained on 04.01.2022.
  • Stage-II Clearance for main forest diversion proposal obtained on 28.12.2022.
  • Stage-I clearance has been accorded on 09.11.2023 for the diversion of 43.2114 Ha of forest land excluding 5.078 Ha of forest land for wayside amenities out of 48.2894 Ha applied for diversion with standard conditions for the additional forest land required.
  • Tree felling and working Permission has been received vide letter no 5896 Date 13.12.2023 from DFO,Koraput.
Tree Cutting Status:
  • Total number of Forest trees felled as on date is 152 nos., out of 152 nos. trees.
  • Total number of non-forest trees felled as on date is 6981 nos., out of 6981 nos. trees.
Environmental Clearance:
Approved on 10-May-2021
Utility shifting estimate sanctioned:
TPSODL:
  • COS order has been issued by RO, NHAI, Odisha vide letter no 3120 dated 13.12.2023.
  • Net cost of electrical work (incl. 18% GST and tender rebate @ 12.48%) to be approved under COS: Rs.5,55,27,509/- towards the electrical utility shifting in Koraput Electrical Division under Change of scope.
  • Total supervision cost @2.5% (incl. 18% GST) to be paid to the TPSODL: Rs.15,72,018/-
OPTCL:
  • COS order has been issued by RO, NHAI, Odisha vide letter no 3120 Date 13.12.2023.
  • Net cost of electrical work (incl. 18% GST and tender rebate @ 12.48%) to be approved under COS: Rs. 10,24,89,274/-
  • Total supervision charges @6% (incl. 18% GST) to be paid to the OPTCL: Rs. 73,96,993/-
PGCIL:
  • COS order has been issued by RO, NHAI, Odisha vide letter no 3120 Date 13.12.2023.
  • Net cost of electrical work (incl. 18% GST and tender rebate @ 12.48%) to be approved under COS: Net cost of electrical work (incl. 18% 16GST and tender rebate @ 12.48%) to be approved under COS: Rs.23,59,93,758/- towards the electrical utility shifting of 400KV PGCIL EHT Lines which are not covered in the Schedule-A of CA.
  • Total supervision cost@2.5% (incl. 18% GST) to be paid to the PGCIL: Rs.79,05,133/-
Issues:
  • 1.In principle approval of COS-2 Proposal (Normative cost estimate) for Civil structures 1 MNB & 06 HPC amounting 2.66 Cr has been received from NHAI HQ on 09.01.2024. COS order estimates are under preparation by Concessionaire.
    • Estimated Positive CoS cost is Rs. 2,65,91,278/-.
    • Cost of Reduction of 2 Nos. of VOPs is Rs. 7,76,14,329/-
  • 1.COS-3 Proposal (Normative cost estimate) for missing structure 01 Major Bridge amounting to 21.58 Cr. has been submitted to RO, NHAI, Bhubaneswar vide E-Office No.236543 Note#1 on 15.01.2024. Further, observation raised by NHAI, HQ on 02.02.2024 vide E-Office No.236543 Note#10 and same has been complied vide E-office (Note#13) dated 10.02.2024. Further, NHAI, HQ raised observation on 18.03.2024 and same was forwarded to IE & DPR Consultant for comments. PD, RO submitted compliance & the file is currently with Sh. Vinod Singh Chaudhary, Dy. Manager (Odisha Division), NHAI, HQ, since 22.04.2024.
EOT:
  • EOT proposal has been already submitted by Concessionaire. Recommendation pending from IE.