| Authority | : National Highways Authority of India |
| Scheme | : Bharatmala Pariyojana (Lot-III) |
| Mode of implementation | : Hybrid Annuity Mode |
| Name of NH | : NH 130 CD |
| Name of Concessionaire | : H G Raipur Visakhapatnam OD-6 Pvt. Ltd. |
| Date of LOA | : 25-Oct-2021 |
| Date of signing of Agreement | : 14-Dec-2021 |
| Appointed Date | : 01-Jun-2022 |
| Scheduled completion date | : 31-May-2024 |
| Likely completion date | : 31- Dec-2024 |
| Construction Period | : 2 Years |
| O&M Period | : 15 Years |
| Length of Project | : 45.500 Km. |
| Bid Project cost | : Rs.1123.11 Crores |
| Sanctioned cost | : Rs.1460.72 Crores |
| Total Capital Cost | : Rs.1294.77{Approved by MoRT&H letter dated 15.07.2021} |
| Independent Engineer | : M/s S.A. Infra Consultants Pvt. Limited in association with M/s Rotrans Infra Projects Pvt. Ltd. |
| Deployment of IE | : 26-May-2022 |
| Contract Amount of IE | : 7.51 Cr. |
| Scheduled Completion of IE Tenure | : 25-May-2026 (48 Months) |
| Safety Consultant | : M/s Techmodec Consultants Pvt. Ltd. |
| Date of deployment | : 29-Nov-2022 |
| Contract Amount | : 1.34 Cr. |
| Tenure Upto | : 28-Nov-2025 (36 Months) |
| 6-lane completed | : 32.580 KM |
| Physical Progress | : 68.00% (Till Date) |
| Financial Progress | : 68.00% |
| Expenditure(payment to concessionaire) | : 682.34 Cr. |