Project Salient Features
Authority : National Highways Authority of India
Scheme : Bharatmala Pariyojana (Lot-III)
Mode of implementation : Hybrid Annuity Mode
Name of NH : NH 130 CD
Name of Concessionaire : H G Raipur Visakhapatnam OD-6 Pvt. Ltd.
Date of LOA : 25-Oct-2021
Date of signing of Agreement : 14-Dec-2021
Appointed Date : 01-Jun-2022
Scheduled completion date : 31-May-2024
Likely completion date : 31- Dec-2024
Construction Period : 2 Years
O&M Period : 15 Years
Length of Project : 45.500 Km.
Bid Project cost : Rs.1123.11 Crores
Sanctioned cost : Rs.1460.72 Crores
Total Capital Cost : Rs.1294.77{Approved by MoRT&H letter dated 15.07.2021}
Independent Engineer : M/s S.A. Infra Consultants Pvt. Limited in association with M/s Rotrans Infra Projects Pvt. Ltd.
Deployment of IE : 26-May-2022
Contract Amount of IE : 7.51 Cr.
Scheduled Completion of IE Tenure : 25-May-2026 (48 Months)
Safety Consultant : M/s Techmodec Consultants Pvt. Ltd.
Date of deployment : 29-Nov-2022
Contract Amount : 1.34 Cr.
Tenure Upto : 28-Nov-2025 (36 Months)
6-lane completed : 32.580 KM
Physical Progress : 68.00% (Till Date)
Financial Progress : 68.00%
Expenditure(payment to concessionaire) : 682.34 Cr.