Authority | : National Highways Authority of India |
Scheme | : Bharatmala Pariyojana (Lot-III) |
Mode of implementation | : Hybrid Annuity Mode |
Name of NH | : NH 130 CD |
Name of Concessionaire | : H G Raipur Visakhapatnam OD-6 Pvt. Ltd. |
Date of LOA | : 25-Oct-2021 |
Date of signing of Agreement | : 14-Dec-2021 |
Appointed Date | : 01-Jun-2022 |
Scheduled completion date | : 31-May-2024 |
Likely completion date | : 31- Dec-2024 |
Construction Period | : 2 Years |
O&M Period | : 15 Years |
Length of Project | : 45.500 Km. |
Bid Project cost | : Rs.1123.11 Crores |
Sanctioned cost | : Rs.1460.72 Crores |
Total Capital Cost | : Rs.1294.77{Approved by MoRT&H letter dated 15.07.2021} |
Independent Engineer | : M/s S.A. Infra Consultants Pvt. Limited in association with M/s Rotrans Infra Projects Pvt. Ltd. |
Deployment of IE | : 26-May-2022 |
Contract Amount of IE | : 7.51 Cr. |
Scheduled Completion of IE Tenure | : 25-May-2026 (48 Months) |
Safety Consultant | : M/s Techmodec Consultants Pvt. Ltd. |
Date of deployment | : 29-Nov-2022 |
Contract Amount | : 1.34 Cr. |
Tenure Upto | : 28-Nov-2025 (36 Months) |
6-lane completed | : 32.580 KM |
Physical Progress | : 68.00% (Till Date) |
Financial Progress | : 68.00% |
Expenditure(payment to concessionaire) | : 682.34 Cr. |